4D-based automation of heavy lift planning in industrial construction projects
Bibliographic record
Abstract
In northern Canada, due to the harsh weather and high labor cost, contractors prefer to using modular construction approach to complete heavy industrial projects, where mobile crane are used for onsite module installations. In current practice, module lifts are often planned manually by rigging engineers. With a large number of heavy lifts to be analyzed per project, the planning process is tedious and error prone. This paper represents a data-driven crane management system with three features: (1) identification of design errors in lifting planning; (2) responses to design changes; and (3) dynamic 3D trajectory-based lifting visualization. It covers two types of crane operations: pick from a fixed location, and pick and walking operation. This developed system helps reduce lifting time and improves safety and quality, where various lifting scenarios need to be analyzed. The system has been implemented at a collaborator company for demonstration and validation.
Fetched live from OpenAlex and de-inverted. Abstracts are not stored in this database: the inverted indexes are 8.6 GB of the frame’s 9.3 GB of text, and the host has 13 GB free.
How this classification was reachedexpand
Full frame distilled prediction
Teacher imitationNot calibrated prevalence, not ground truth. Human validation pending. Learned from the 10,348 direct Codex labels and 10,348 direct Gemma labels. Candidate is the union of thresholded teacher heads; consensus is their intersection. These outputs are machine_predicted_unvalidated and are not human labels or direct frontier model labels.
Codex and Gemma teacher scores by category
| Category | Codex | Gemma |
|---|---|---|
| Metaresearch | 0.000 | 0.000 |
| Meta-epidemiology (narrow) | 0.000 | 0.000 |
| Meta-epidemiology (broad) | 0.000 | 0.000 |
| Bibliometrics | 0.000 | 0.000 |
| Science and technology studies | 0.000 | 0.000 |
| Scholarly communication | 0.000 | 0.000 |
| Open science | 0.000 | 0.000 |
| Research integrity | 0.000 | 0.000 |
| Insufficient payload (model declined to judge) | 0.000 | 0.000 |
Machine scores (provisional)
The two teacher heads of the student model, read on this work. A score orders the frame for review; it never asserts a category, and the validation status ships verbatim with every row.
Baseline scores from an immature model (maturity gate not passed, 7 training rounds). Scores rank; they never assert a category.
score_only:v0-immature-baseline · verbatim from the scoring run: score_only means the number may rank works, and no category label ships from itClassification
machine, unvalidatedMachine predicted; a candidate call from one teacher head, not a consensus.
How this classification was reached, model by model and score by score, is at the end of the page under "How this classification was reached".