Uncertainty Management Associated With Project Scheduling in Mine Construction: A Coal Mining Case Study
Bibliographic record
Abstract
Abstract Due to the cyclical nature of commodity prices, the profitability of mining projects relies on proper timing. To ensure optimal profits, mines should be brought online at the time, which maximizes the potential value of the asset. In this paper, a coking coal mine construction case is used to demonstrate the effectiveness of scheduling large-scale construction projects with uncertain durations under price cyclicality. Project parameters are obtained stochastically via Monte Carlo sampling, allowing for the influence of uncertainty to be quantified. The critical path method and linear programming are employed to analyze the results and to optimize the construction process, ensuring the maximum value of the mining project. The parameters are repeatedly sampled to obtain distributions of possible project outcomes, allowing for risk and sensitivity quantification. The optimal schedule for construction was determined to be 247 weeks, with a most likely value of $813 million.
Fetched live from OpenAlex and de-inverted. Abstracts are not stored in this database: the inverted indexes are 8.6 GB of the frame’s 9.3 GB of text, and the host has 13 GB free.
How this classification was reachedexpand
Full frame distilled prediction
Teacher imitationNot calibrated prevalence, not ground truth. Human validation pending. Learned from the 10,348 direct Codex labels and 10,348 direct Gemma labels. Candidate is the union of thresholded teacher heads; consensus is their intersection. These outputs are machine_predicted_unvalidated and are not human labels or direct frontier model labels.
Codex and Gemma teacher scores by category
| Category | Codex | Gemma |
|---|---|---|
| Metaresearch | 0.001 | 0.000 |
| Meta-epidemiology (narrow) | 0.000 | 0.000 |
| Meta-epidemiology (broad) | 0.000 | 0.000 |
| Bibliometrics | 0.001 | 0.001 |
| Science and technology studies | 0.000 | 0.000 |
| Scholarly communication | 0.000 | 0.000 |
| Open science | 0.000 | 0.001 |
| Research integrity | 0.000 | 0.002 |
| Insufficient payload (model declined to judge) | 0.000 | 0.000 |
Machine scores (provisional)
The two teacher heads of the student model, read on this work. A score orders the frame for review; it never asserts a category, and the validation status ships verbatim with every row.
Baseline scores from an immature model (maturity gate not passed, 7 training rounds). Scores rank; they never assert a category.
score_only:v0-immature-baseline · verbatim from the scoring run: score_only means the number may rank works, and no category label ships from itClassification
machine, unvalidatedMachine predicted; a candidate call from one teacher head, not a consensus.
How this classification was reached, model by model and score by score, is at the end of the page under "How this classification was reached".