MétaCan
Menu
Back to cohort
Record W3048039688 · doi:10.1061/9780784483206.055

Crossing the Red: Managing Construction Changes on a Challenging 1200 mm Microtunnelling River Crossing in Winnipeg, Manitoba, Canada

2020· article· en· W3048039688 on OpenAlex
Adam Braun, Nathan Kehler, J J S Thompson, Stacy Cournoyer

Why this work is in the frame

A frame that forgets how it found something cannot be audited. These are the routes that admitted this work.

affAt least one author lists a Canadian institution in the pinned OpenAlex snapshot.
aboutThe title or abstract carries a Canadian signal from the geographic lexicon.

Bibliographic record

VenuePipelines 2020 · 2020
Typearticle
Languageen
FieldEngineering
TopicGeotechnical Engineering and Analysis
Canadian institutionsUniversity of WinnipegManitoba Beekeepers' AssociationAecom (Canada)
Fundersnot available
KeywordsLevel crossingComputer scienceGeographyArchaeology

Abstract

fetched live from OpenAlex

The Northeast Interceptor services approximately 2,300 ha (5,685 acres) of land in the northeast quadrant of the City of Winnipeg (Manitoba, Canada). The 1,800 mm (72”) Interceptor crosses the Red River using a multiple-barrel inverted steel siphon configuration prior to it’s final leg before reaching the City’s largest wastewater treatment plant. The original siphon crossing, built in 1971, was at capacity during large wet weather events and required additional capacity to meet development plans and reduce upstream basement flooding risk. Thus, plans were developed to install an additional siphon. The size and construction methodology for the river crossing evolved through both the design and construction of the project. Originally starting life as a 600 mm (24”) horizontal directional drill crossing, system hydraulic requirements dictated the installation of a larger 900 to 1200 mm (36” to 48”) crossing to meet the desired design objectives. Due to the geotechnical, geometric, and surface use constraints, a 900 mm (36”) microtunnelled crossing was tendered. To facilitate microtunnelling through underlying limestone bedrock in an area where external access is extremely limited, the contractor (Ward and Burke Microtunnelling) opted to install a single pass 1200 mm (48”) siphon, increasing the capacity of the new crossing. Further changes to the project were proposed by the contractor and to an extent accepted by the project team. They included a vertically curved microtunnelling drive, eliminating the need to construct shafts within the underlying limestone aquifer, changes to the chamber designs to suit their preferred construction methods, and an alternative connection configuration to reduce tie-in risks. The challenge, as with any contractor driven design change, is to primarily ensure the original design intent and functionality of the project is not compromised. Secondarily, where construction risks have been shifted to other portions of the work, one must ensure they are of an acceptable magnitude and/or have been sufficiently mitigated. While this paper discusses the project as a whole, it primarily focuses on the evolution of the crossing design from inception to completion of construction. Managing design changes during construction is a critical component to any large capital project. This paper details AECOM’s efforts to manage proposed changes during construction, complete with a lessons learned and recommendations for future complex tunneling projects.

Fetched live from OpenAlex and de-inverted. Abstracts are not stored in this database: the inverted indexes are 8.6 GB of the frame’s 9.3 GB of text, and the host has 13 GB free.

Full frame distilled prediction

Teacher imitation

Not calibrated prevalence, not ground truth. Human validation pending. Learned from the 10,348 direct Codex labels and 10,348 direct Gemma labels. Candidate is the union of thresholded teacher heads; consensus is their intersection. These outputs are machine_predicted_unvalidated and are not human labels or direct frontier model labels.

metaresearch head score (Codex)0.000
metaresearch head score (Gemma)0.000
Version: codex-gemma-dda1882f352aValidation status: machine_predicted_unvalidated
Candidate categoriesMeta-epidemiology (narrow)
Consensus categoriesnone
DomainCandidate signal: none · Consensus signal: none
Study designCandidate signal: Simulation or modeling · Consensus signal: Simulation or modeling
GenreCandidate signal: Empirical · Consensus signal: Empirical
Teacher disagreement score0.182
Threshold uncertainty score1.000

Codex and Gemma teacher scores by category

CategoryCodexGemma
Metaresearch0.0000.000
Meta-epidemiology (narrow)0.0000.000
Meta-epidemiology (broad)0.0000.000
Bibliometrics0.0000.001
Science and technology studies0.0000.000
Scholarly communication0.0000.000
Open science0.0000.000
Research integrity0.0000.001
Insufficient payload (model declined to judge)0.0000.000

Machine scores (provisional)

The two teacher heads of the student model, read on this work. A score orders the frame for review; it never asserts a category, and the validation status ships verbatim with every row.

Baseline scores from an immature model (maturity gate not passed, 7 training rounds). Scores rank; they never assert a category.

Opus teacher head0.015
GPT teacher head0.193
Teacher spread0.178 · how far apart the two teachers sit on this one work
Validation statusscore_only:v0-immature-baseline · verbatim from the scoring run: score_only means the number may rank works, and no category label ships from it