A Multi-Objective Scheduling Algorithm for Multi-Mode Resource Constrained Projects in the Presence of Uncertain Resource Availability

2021· article· en· W3125454972 on OpenAlexaff
Mehrdad Pouya, Aidin Delgoshaei, Ahad Ali

Bibliographic record

VenueBrazilian Journal of Operations & Production Management · 2021
Typearticle
Languageen
FieldEngineering
TopicBIM and Construction Integration
Canadian institutionsToronto Metropolitan University
Fundersnot available
KeywordsComputer scienceScheduling (production processes)ScheduleFair-share schedulingDynamic priority schedulingGenetic algorithm schedulingMathematical optimizationJob shop schedulingHeuristicRate-monotonic schedulingOperations researchIndustrial engineeringEngineeringMathematicsArtificial intelligence

Abstract

fetched live from OpenAlex

Goal: The issue of resource allocation is a major concern for project engineers in the scheduling process of a project. Resources over-allocation are often seen in practice after the scheduling of a project, which makes scheduling unhelpful. Modifying an over-allocated schedule is very complicated and requires a lot of effort and time. Besides, during the scheduling process of resource-constrained projects in the constructing companies, managers should concern more than one objective at the same time. This research aims to propose a new heuristic algorithm for minimizing project completion time, cost or maximizing quality of execution of activities simultaneously while multi-mode activities are taken into consideration. Design / Methodology / Approach: In this research, a new heuristic method is proposed for solving multi-objective scheduling problem for multi-mode resource constrained project scheduling problems (MRCPSPs) where the aim is maximizing the net present value (NPV) of project, minimize completion time and maximize the quality of executing activities simultaneously and along with emerging the uncertainty of resources availability and activity durations. The proposed method is then coded by Matlab® 2016. Results: The outcomes of solving small, medium and large scale case studies, the following results achieved: (i) the algorithm could solve all problems in different circumstances with no difficulties; (ii) the large scale problems (with 200 activities, 20 resources and 3 execution modes for each activity) could be solved in 4.43 seconds. (iii) in none of the studied cases over-allocation problem. The proposed method can be considered among the fastest scheduling algorithms found in the literature. In addition, it is found that makespan, NPV and quality have co-relation must be taken into consideration during the scheduling process. Limitations of the investigation: The main limitations of this research is that it only covers resource constrained project scheduling. Moreover, risk factors associated with the objectives of this research have yet to be addressed in future research studies. Practical implications: The performance of the algorithm is validated by using 24 series of dataset that are found in the literature. In order to verify its performance in real practice, it has been applied for a part of a construction project in Malaysia. The outcomes indicated that the algorithm scheduled the problem with 23 activities, 5 constrained resources and 2 execution modes in less than a second and with no over-allocations. The proposed multi-objective algorithm allows the project managers to consider NPV, completion time and quality of activities while scheduling a multi-mode project. In practice, this algorithm can provide a better atmosphere for managers while they aim to consider more than one objective during the scheduling process. Originality / Value: The proposed algorithm is original and can be of great value for future studies and managers in preventing resource over-allocation during the scheduling of multi-objective multi-mode resource constraint project scheduling. Moreover, it can help project managers to find near optimum solutions for complex multi-objective resource constraint projects faster and also with more accuracy.

Fetched live from OpenAlex and de-inverted. Abstracts are not stored in this database: the inverted indexes are 8.6 GB of the frame’s 9.3 GB of text, and the host has 13 GB free.

How this classification was reachedexpand

Full frame distilled prediction

Teacher imitation

Not calibrated prevalence, not ground truth. Human validation pending. Learned from the 10,348 direct Codex labels and 10,348 direct Gemma labels. Candidate is the union of thresholded teacher heads; consensus is their intersection. These outputs are machine_predicted_unvalidated and are not human labels or direct frontier model labels.

metaresearch head score (Codex)0.001
metaresearch head score (Gemma)0.000
Version: codex-gemma-dda1882f352aValidation status: machine_predicted_unvalidated
Candidate categoriesnone
Consensus categoriesnone
DomainCandidate signal: none · Consensus signal: none
Study designCandidate signal: Simulation or modeling · Consensus signal: Simulation or modeling
GenreCandidate signal: Methods · Consensus signal: Methods
Teacher disagreement score0.383
Threshold uncertainty score0.506

Codex and Gemma teacher scores by category

CategoryCodexGemma
Metaresearch0.0010.000
Meta-epidemiology (narrow)0.0000.000
Meta-epidemiology (broad)0.0000.000
Bibliometrics0.0000.001
Science and technology studies0.0000.000
Scholarly communication0.0000.000
Open science0.0000.000
Research integrity0.0000.000
Insufficient payload (model declined to judge)0.0000.000

Machine scores (provisional)

The two teacher heads of the student model, read on this work. A score orders the frame for review; it never asserts a category, and the validation status ships verbatim with every row.

Baseline scores from an immature model (maturity gate not passed, 7 training rounds). Scores rank; they never assert a category.

Opus teacher head0.027
GPT teacher head0.283
Teacher spread0.256 · how far apart the two teachers sit on this one work
Validation statusscore_only:v0-immature-baseline · verbatim from the scoring run: score_only means the number may rank works, and no category label ships from it

Classification

machine, unvalidated

Machine predicted; a candidate call from one teacher head, not a consensus.

The models applied no category: nothing in the taxonomy fit this work.
Study designSimulation or modeling
Domainnot available
GenreMethods

How this classification was reached, model by model and score by score, is at the end of the page under "How this classification was reached".

Quick stats

Citations3
Published2021
Admission routes1
Has abstractyes

Explore more

Same venueBrazilian Journal of Operations & Production ManagementSame topicBIM and Construction IntegrationFrench-language works237,207